Print
Press Enter to show all options, press Tab go to next option

10600 S Interchange Update

Post Date:04/23/2018 5:22 PM

Work to be completed includes overhead sign adjustments and a concrete coating on all new concrete, including inside the 10600 South tunnel and on top of the 10600 South bridge. Be prepared to follow detour signs and/or highway patrol directing traffic.

The following dates and associated work details are below: 

  • April 26 - 27: Lanes will be shifted on the Monroe Street ramp, Mall Ring Road, and the intersection of Monroe/Mall Ring Road to accommodate daytime striping activities.
  • April 30 - May 1: The 10600 South tunnel will be closed for each night starting at 8:00 PM to 7:00 AM. Lanes will also be shifted on the northbound I-15 off-ramp between 7:00 PM and 4:00 AM and east-west across the 10600 South bridge from 7:00 PM to 8:00 AM.
  • May 2 - 4: Lane closures on I-15 northbound and southbound from 7:00 PM to 4:00 AM.  

Be alert to shifting lanes, construction-related vehicles entering and exiting the roadway, and watch for construction and detour signs.

**All work and dates are weather dependent. 

Contact Our Public Involvement Team

Phone: 801-228-0022, Option 2
Email: southvalley@utah.gov